Four hundred GPUs translated into fifty HGX nodes and what each node carries

A B300 server is 8 GPUs, so 4,096 GPUs is 512 machines. Every figure below is built from that, using prices listed on our own inventory today.

The hardware

A new B300 HGX node lists at $563,000, so 512 of them is $288,256,000. Refurbished lines have sat at $530,000, which would take the same cluster to $271,360,000, a $16.9m difference for hardware that does the same work. That spread is why condition is a commercial question and not a technical one.

Power and space

At roughly 14 kW per node, 512 nodes draw about 7.2 MW before any cooling overhead. At the North American wholesale average of about $196 per kW per month, that is $1,405,404 a month, or $50,594,544 across 3 years. In a constrained market at $400 per kW the same footprint costs $103,254,000, which is a $52m swing driven entirely by where you put it.

At 14 kW per node you are fitting perhaps four nodes to a rack, so this is a 128-rack deployment and a genuine multi-megawatt facility conversation, not a colocation order form.

The fabric

Every node needs transceivers at both ends of every link, and 800G class optics run about $1,000 each. Budget roughly $16,000 per node for optics and its share of switching, which is $8,192,000 across the cluster. It is the line most commonly missing from a first-pass budget, and it is bigger than most people guess by an order of magnitude.

Getting it there

At 512 crated nodes this is freight on the critical path, not a shipping afterthought. Duties, import VAT and handling vary by destination and are frequently a seven-figure line on a cluster this size. If you have no registered entity in the destination country you also need an Importer of Record, and arranging one late is a common reason hardware waits at a border while the facility bill runs.

The shape of it

Hardware $288,256,000. Colocation and power $50,594,544 over 3 years in North America. Optics and fabric $8,192,000. Freight, duties and commissioning on top, varying by route. The accelerators are about 83% of the bill, which is why they get the attention, and the other 17% is where the schedule risk lives.

For comparison, renting the same 4,096 GPUs at $4.00 per GPU-hour for 3 years is $430,571,520, with no asset at the end.

We build this table against a real destination, a real density and a real utilisation before anyone commits. Price the hardware on the live inventory, the facility side on colocation and power, or run your own numbers with the cluster cost calculator.

Straight answers

Asked first, answered straight.

How much does a 4,096-GPU B300 cluster cost?

About $288,256,000 in hardware at $563,000 per 8-GPU node, plus roughly $50,594,544 of colocation and power over 3 years at North American rates, plus about $8,192,000 in optics and fabric, before freight, duties and commissioning.

How much power does a 512-node B300 cluster draw?

Roughly 7.2 MW at about 14 kW per node, before cooling overhead. At four nodes per rack that is around 128 racks, which makes it a multi-megawatt facility project rather than a colocation order.

Is it cheaper to buy or rent 4,096 B300 GPUs?

Buying is $288,256,000 in hardware against $430,571,520 to rent the same GPUs for 3 years at $4.00 per GPU-hour. Once colocation, power and fabric are added the owned position is around $347m, still materially cheaper, and it leaves you holding the asset.

Working through this on a real requirement? Twenty minutes with the desk, no pitch, no quote at the end of it. We run your numbers, not ours.

Talk to the desk
Keep reading

Live GPU inventory →

Cluster cost calculator →

Buy B300 →

Talk to the desk

Working through this on a real requirement?

Twenty minutes with the desk, no pitch and no quote at the end of it. Tell us roughly what you need and we will come back within one business day.

Acknowledged within one hour, first sourcing pass within one business day.

Sent. We are on it.

Your enquiry has landed with the desk. Acknowledged within one hour.